How long does SolarOcta installation phase take?

From the time of sales confirmation (advance payment), it usually takes 3-4 weeks for installation to start. The on-site construction / civil work phase is typically, 7 days for residential projects, and 1-2 months for larger commercial projects.

The time required for obtaining utility permissions is ever-evolving, & varies across states & regions:

1. In Delhi, it typically ranges from 4-6 weeks.
2. In Haryana, it depends on the utility company,city & ranges between 4-6 weeks.
3. In Uttar Pradesh , it generally takes 8 weeks.